Monopile Upending Frame (MUF)
Monday 10 August 2009
The Monopile Upending Frame (MUF) was designed and supplied by IHC Gusto BV to MPI’s specification to facilitate the handling of large offshore piles.

The Monopile Upending Frame (MUF) was designed and supplied by IHC Gusto BV to MPI’s specification to facilitate the handling of large offshore piles from the horizontal transportation position to vertical without the need for a large capacity crane.
The pile is inserted into the MUF (using strand jacks or trailers) to a position where the centre of gravity is just beyond the hinge point and is gripped by hydraulic cylinders.
The pile is then rotated in the upending frame under its own weight controlled by winches. Once vertical the pile can be lowered to the sea bed by jacking down the installation vessel (if possible) or releasing the grips.
General Information
Total Length: 13,250 mm
Maximum Width (Upend Frame): 9,060 mm
Maximum Width (Base Frame): 13,200 mm
Pile Diameter: 4,000 – 6,000 mm
Maximum Pile Length: 61.2 m
Maximum Pile Weight: 600 Tonnes
Environmental
Maximum Operational wind Speed: 20 m/s
Maximum Operational Current (water depth 15m): 2 m/s
Maximum Operational Current (water depth 15 – 35m): 1 m/s
Maximum Vessel Heel: +/- 0.3 Deg
Maximum Vessel Trim: +/- 0.3 Deg
LATEST NEWS
MPI Offshore Scoop Industry Award Thursday 16 February 2012
MPI Offshore have been announced as the inaugural winner of the Offshore Renewables award at the recent Annual Offshore Support Journal awards held in London.
READ MOREMPI Offshore Takes Delivery of MPI Discovery Friday 4 November 2011
MPI Offshore Limited (MPI) is pleased to announce the delivery, in Qidong, People’s Republic of China, of the MPI Discovery, the second of two state-of-the art wind turbine installation vessels to be built at the Cosco Qidong Shipyard. The vessel left the Shipyard today, 28 October 2011.
READ MOREE.ON Secures State-Of-The-Art Offshore Vessel from MPI Wednesday 29 June 2011
E.ON Climate & Renewables and MPI-Vroon have today signed a 6 year charter for the MPI Discovery, a specialist vessel used in the construction of offshore wind farms.
READ MOREPROJECTS
Thanet Offshore Wind Farm
Wednesday 5 August 2009
During December '08 MPI Offshore finalized a third Party charter to take Resolution to assist with the construction of the foundations for the Thanet Offshore Wind Farm, now owned by Vattenfall the Swedish/German Utility.
READ MORE