21-12-2012 - MPI Dorothea equipped with Maxcess system
Friday 21 December 2012
MPI’s wind-turbine-maintenance vessel, MPI Dorothea, has recently been equipped with the Maxcess T12 system. The vessel’s charterer, Scira, ordered the system earlier in 2012 with the aim of enhancing safety and transfer performance on board MPI Dorothea. The Maxcess system connects to the turbine, ensuring a stable platform for transfer.

Scira currently charters two identical 18m South Boats, operated by MPI Workboats, for the transfer of Siemens’ technicians involved in O&M activities. A comparison of transfer performance between the two vessels and an assessment of reliability of the Maxcess system is planned for the coming months.
Scira estimates that if it can increase access from its current average of 1.1m to 1.8m wave height, it will achieve an increase of 40% in working time. This should ensure that Scira’s operations are not only safer, but significantly more effective with the introduction of Maxcess to its O&M activities.
The vessel started operations at Scira’s Sheringham Shoal site mid-December 2012.
LATEST NEWS
24-04-2013 - MPI Resolution awarded GeoSea Charter Party Wednesday 24 April 2013
MPI Offshore is pleased to announce the award of a charter party in respect of MPI Resolution by GeoSea N.V., subsidiary of the Belgian based DEME Group.
READ MORE22-04-2013 Day One of the E.ON Journey Monday 22 April 2013
In June 2011, E.ON and MPI entered into a long-term partnership for a six-year charter of MPI Discovery. Nearly two years later, 28 March 2013 marked the first day of the charter period.
READ MORE11-03-2013 - MPI Adventure awarded Trianel Wind Farm Borkum Charter Party Monday 11 March 2013
MPI Offshore is pleased to announce the award of a charter party in respect of MPI Adventure by Trianel Windkraftwerk Borkum GmbH & Co. KG for the installation of wind turbine generators on the Trianel Borkum Offshore Wind Farm situated off the Northern Coast of Germany.
READ MOREPROJECTS
05-08-2009 - Thanet Offshore Wind Farm
Wednesday 5 August 2009
During December 2008 MPI Offshore finalized a Third Party charter to take MPI Resolution to assist with the construction of the foundations for the Thanet Offshore Wind Farm, now owned by Vattenfall, the Swedish/German Utility.