Lynn and Inner Dowsing Foundation Completion

Saturday 15 December 2007

On the 5th December 2007 the works to install the last foundation at the Lynn and Inner Dowsing Wind Farm were completed. This significant achievement heralded the completion of 54 turbine foundations, including a number of the inter array cables.

To bring this achievement about, detail planning and engineering was essential to optimise the transport of foundation components from the fabricators works in Belgium, by barge, to the port of Vlissingen. At the port, Resolution self loaded 5 foundation sets at a time from the delivery barge, then returned to the LID field to install them.

Quite early on in the installation programme, a number of piles reached premature refusal and Resolution had to be mobbed with drilling equipment to drill/drive the piles to finished level. In parallel with these early piles the array cables were installed by the ROV, LBT1. A vehicle which has been specifically developed by MPI to install the array cables whilst the foundations (or turbines) are being installed. Resolutions multi-tasking ability for transportation, installation and cable works were tested to the full during this phase of the project.

In the latter period of the installation programme and with all the drilling completed, almost 50% of foundations were installed from October to the completion in early December. During that time, the 60 plus onboard installation crews worked seamlessly, 24/7, to achieve such a phenomenal performance.

From start to finish Resolution's performance was faultless, coping magnificently with the North Sea autumn/winter conditions for the transit, in-field movements and jacking operations. With such a track record, Resolution has consolidated her position as one of the prime offshore wind farm installation vessels in the world.

Our Client, Centrica Renewable Energy Ltd, is very pleased with this performance and reinforces the decision they made in spring 2006 to long term charter the Resolution for all their foreseeable offshore wind farm installations.

Go back

All Energy 2012 - Aberdeen, May 23rd-24th 2012

LATEST NEWS

MPI Offshore Scoop Industry Award Thursday 16 February 2012

MPI Offshore have been announced as the inaugural winner of the Offshore Renewables award at the recent Annual Offshore Support Journal awards held in London.

READ MORE

MPI Offshore Takes Delivery of MPI Discovery Friday 4 November 2011

MPI Offshore Limited (MPI) is pleased to announce the delivery, in Qidong, People’s Republic of China, of the MPI Discovery, the second of two state-of-the art wind turbine installation vessels to be built at the Cosco Qidong Shipyard. The vessel left the Shipyard today, 28 October 2011.

READ MORE

E.ON Secures State-Of-The-Art Offshore Vessel from MPI Wednesday 29 June 2011

E.ON Climate & Renewables and MPI-Vroon have today signed a 6 year charter for the MPI Discovery, a specialist vessel used in the construction of offshore wind farms.

READ MORE

PROJECTS

Thanet Offshore Wind Farm

Thanet Offshore Wind Farm
Wednesday 5 August 2009

During December '08 MPI Offshore finalized a third Party charter to take Resolution to assist with the construction of the foundations for the Thanet Offshore Wind Farm, now owned by Vattenfall the Swedish/German Utility.

READ MORE