MPI Secure London Array Charter for Adventure

Wednesday 3 February 2010

The consortium developing the London Array, the world’s largest offshore wind farm, have today announced that a charter has been awarded to MPI Offshore Ltd to use Adventure for the installation of foundations and turbines for the first phase of what potentially will be the worlds first 1GW offshore wind farm

MPI Adventure is currently being built at Cosco Nantong in China and will be delivered to start construction in April 2011.  MPI Adventure and MPI Discovery are second generation vessels based on the successful MPI Resolution.  Their increased capacities in terms of transport, jacking and cargo make them capable of installing more than any other vessel in the market today.

Richard Rigg, Project Director for London Array, said: “These are the final major construction contracts to be signed for London Array, which has now moved as a project from the development phase into full construction.

“These vessels are critical to the successful installation of the wind turbines and their foundations and we are delighted to be working with such experienced contractors.”

Once complete, the scheme will be the world’s largest, and the first 1GW, offshore wind farm. Sited in the Thames Estuary, the project will supply enough power for around 750,000 homes – or a quarter of Greater London homes – and displace the emission of 1.9m tonnes of CO2 every year.

London Array will be built around 20km off the coasts of Kent and Essex. The wind farm will be installed on a 245km2 site and will be built in two phases. Phase One, planned to be complete in 2012, will cover 90km2 and include 175 turbines with a combined capacity of 630MW.  If approved, the second phase will add enough capacity to bring the total to 1,000MW.

The project consortium partners have the following shareholdings: DONG Energy owns 50%, E.ON has 30% and Masdar has a 20% stake.

Go back

Renewable UK 2010 - Glasgow, November 2nd-4th 2010

LATEST NEWS

100 Turbines in less than 100 days Thursday 26 August 2010

More than a month ahead of schedule, Vestas completes the installation of the 100th turbine at the Thanet Offshore Wind Farm.

READ MORE

MPI Workboats to exercise option for further workboat Wednesday 4 August 2010

MPI Workboats are happy to announce that it has exercised an option for the construction of a further state of the art, purpose built wind farm support aluminium catamaran for delivery in June 2011.

READ MORE

MPI Celebrates Keel Laying Wednesday 7 July 2010

On 15 May 2010 MPI Offshore proudly participated in the keel-laying ceremony for “MPI Discovery”, the second of two state-of-the-art wind turbine installation vessels, currently under construction at the Cosco Nantong Shipyard in China.

READ MORE

PROJECTS

Thanet Offshore Wind Farm

Thanet Offshore Wind Farm
Wednesday 5 August 2009

During December '08 MPI Offshore finalized a third Party charter to take Resolution to assist with the construction of the foundations for the Thanet Offshore Wind Farm, now owned by Vattenfall the Swedish/German Utility.

READ MORE