May 2011 – December 2012

Following delivery of the vessels, in May and December 2011 respectively, the MPI Adventure and MPI Discovery’s inaugural contracts were with London Array Limited on the London Array Wind Farm Project – at that time the world’s largest consented offshore wind project.

Mobilised with bespoke sea-fastenings to allow the transportation of six complete offshore turbines and equipped with a 1000t Gusto crane and state-of-the-art dynamic positioning she was perfectly equipped for the rigors of a demanding offshore installation programme. Operating out of Esbjerg in Denmark, installation of the 111No WTGs was completed in December 2012.