Robin Rigg Wind Farm


Robin_rigg_wind_farm_large_image

01/07/2015

December 2007 – November 2008

In January 2009 MPI Resolution loaded the final four monopiles of in total 60 to finish the foundations on the Robin Rigg Wind Farm. This sees the culmination of two third-party-charters to E.ON Renewables.

The first of which saw MPI Resolution leaving the Lynn and Inner Dowsing project owned by Centrica in mid-December 2007 and sailing to the Robin Rigg field in the Irish Sea. Once on location MPI Resolution installed eight foundations before returning to Esjberg in February 2008. After finishing the turbine erection for Centrica in mid-July, MPI Resolution again returned to the Robin Rigg Wind farm to install the remaining 52 foundations. The project was completed in January 2009.