Kentish Flats

Tuesday 11 August 2009

M.T. Hojgaard awarded the subcontract to MPI in May 2004 for the load out, transport and installation of 30 WTG Monopiles and Transition Pieces. MTH crews, supported by MPI personnel, operated the foundation installation equipment.

The foundation components were collected from the manufacturer's works based at Hoboken, Belgium. Resolution's deck was then loaded with 6 sets of foundation components - 5 separate load out operations were needed to complete the 30 foundations. The approximate deck pay load was 2500 tonnes per load out and all components were craned aboard by means of Resolution's 300 tonne construction crane.

Monopile weights were in the range of 150 to 185 tonnes and lengths 33 to 41 metres. Transitions weighed 70 tonnes and were completely fitted out with all platforms, J-tubes, boat landings and cathodic protection. The transitions were stowed vertically on Resolution's deck which minimised damage to the finished paint system.

Resolution's aft deck was fitted with installation equipment which included the pile hammer (160 tonnes) the pile gripper (50 tonnes), grout spread and six 20 feet grout containers, pile up-ending tool and pile tailing frame plus all associated power packs, hydraulic hose reels and other ancillary equipment.

Resolution provided a complete turn-key service for foundation collection, transport, and installation, on board accommodation was provided for the 30 plus construction team members and client representatives working around the clock. No other support vessels were necessary, other than small work boat for local deliveries and personnel transfers at the Kentish Flats site.

The programme commenced with the first load out at Hoboken and was a demanding 58 days including an allowance of 9 days weather down time.

Operational and environmental conditions were extremely onerous throughout the installation period. Detailed planning was essential to maintain smooth, continuous and efficient installation operations. Leg penetrations were regularly 7 to 8 metres and on occasions as deep as 10 to 11 metres. Low water at most monopile locations was nominally 4 metres; Resolution's draft fully loaded is also nominally 4 metres. Hence to maintain the programme, jack-down at one location, moving and jacking-up at the next location had to be achieved within one high water tide.

MPI worked closely with their MTH team partners to achieve this optimum programme, which averaged overall, a foundation installed every 2 days, including all load out and weather downtime.

Go back

Renewable UK 2010 - Glasgow, November 2nd-4th 2010

LATEST NEWS

MPI Celebrates Launching MPI Adventure Monday 6 September 2010

On 27 August 2010, MPI Offshore proudly held the launching ceremony of “MPI Adventure”, the first of two state-of-the art wind turbine installation vessels, currently under construction at the Cosco Nantong Shipyard in China.

READ MORE

100 Turbines in less than 100 days Thursday 26 August 2010

More than a month ahead of schedule, Vestas completes the installation of the 100th turbine at the Thanet Offshore Wind Farm.

READ MORE

MPI Workboats to exercise option for further workboat Wednesday 4 August 2010

MPI Workboats are happy to announce that it has exercised an option for the construction of a further state of the art, purpose built wind farm support aluminium catamaran for delivery in June 2011.

READ MORE

PROJECTS

Thanet Offshore Wind Farm

Thanet Offshore Wind Farm
Wednesday 5 August 2009

During December '08 MPI Offshore finalized a third Party charter to take Resolution to assist with the construction of the foundations for the Thanet Offshore Wind Farm, now owned by Vattenfall the Swedish/German Utility.

READ MORE