Projects


On this page you can find information on both current and historic MPI Offshore Projects.


MPI Adventure @ Amrumbank © Cor Draijer_installing 17th turbine_DSCN2087-cropped

Amrumbank West – MPI Adventure

01/07/2015

January 2014 – September 2015

Between January 2014 and September 2015, MPI Adventure, MPI Discovery and MPI Enterprise have worked on the Amrumbank West Offshore Wind Farm. (more…)

OLYMPUS DIGITAL CAMERA

Humber Gateway – MPI Resolution

August 2013 – April 2015

Between August 2013 and April 2015, MPI Resolution and MPI Discovery installed the foundations of the Humber Gateway Offshore Wind Farm. In the second half of 2014 and early 2015, MPI Resolution installed 73 Vestas 3.0MW turbines. (more…)

MPI Resolution loaded

Northwind Project – Zeebrugge Belgium

June 2013 – March 2014

During the construction of the Northwind offshore windfarm, a number of MPI and Vroon vessels have been employed on this project. The windfarm, situated off Zeebrugge in Belgium, consists of more than 70 offshore wind turbines, providing 216 MW, enough power for 120,000 households. (more…)

MPI Adventure_crop

Trianel Borkum Offshore Wind Farm

June 2013 – June 2014

Back in June 2103, MPI Offshore was pleased to announce the award of a charter party in respect of MPI Adventure by Trianel Windkraftwerk Borkum GmbH & Co. KG for the installation of wind turbine generators on the Trianel Borkum Offshore Wind Farm situated off the Northern Coast of Germany. (more…)

MPI Resolution © RIBBE (16)

Docking Shoal – MPI Resolution

May 2013

In May 2013, MPI Resolution facilitated the removal of the lattice structure of the Docking Shoal met mast.

MPI Discovery_Sweden-First-Vestas-V112-3_0-MW-Offshore-Turbines-Installed

First Vestas’ Offshore Turbines installed – Kårehamn, Sweden

March 2013 – July 2013

MPI Discovery installed sixteen V112-3.0 MW offshore turbines on the 48 MW offshore project in Kårehamn, Sweden. In addition, the turbines were also part of the first shipment of turbines from Vestas’ pre-assembly facility in Esbjerg, Denmark. (more…)

June 2013_EDF

Teesside offshore wind farm

December 2012 – May 2013

EDF Energy Renewables has completed the construction of its Teesside offshore wind farm near Redcar. (more…)

MPI Adventure

Blyth – MPI Adventure

September 2012 – November 2012

Between September 2012 and November 2012, MPI Adventure was used for the transportation and installation of a met mast on the Blyth offshore wind farm.

 

London Array - last nacelle 003

London Array Offshore Windfarm

May 2011 – December 2012

Following delivery of the vessels, in May and December 2011 respectively, the MPI Adventure and MPI Discovery’s inaugural contracts were with London Array Limited on the London Array Wind Farm Project – at that time the world’s largest consented offshore wind project. (more…)

_L1001702

LINCS Offshore Windfarm

March 2011 – May 2013

MV MPI Resolution has been contracted to Centrica Renewables on the Lincs Wind Farm Project and successfully completed the installation of WTG foundations (monopiles and TPs) from April 2012 a smooth transition in June 2012 saw it move onto the topside contract installing tower sections, nacelles and blades. (more…)

Burbo Bank, Gunfleet Sands 1, Rhyl Flats – MPI Resolution

August 2010 – December 2010

Between August and December 2010, MPI Resolution was used for several O&M works on the Burbo Bank, Gunfleet Sands 1 and Rhyl Flats wind farms. Amongst others, works included the change out of blade bearings.

MPI Resolution Thanet

Thanet Offshore Wind Farm

April 2009 – February 2010

During December 2008 MPI Offshore finalized a third-party charter to take MPI Resolution to assist with the construction of the foundations for the Thanet Offshore Wind Farm,  owned by Vattenfall, the Swedish/German utility. (more…)

Robin_rigg_wind_farm_large_image

Robin Rigg Wind Farm

December 2007 – November 2008

In January 2009 MPI Resolution loaded the final four monopiles of in total 60 to finish the foundations on the Robin Rigg Wind Farm. This sees the culmination of two third-party-charters to E.ON Renewables. (more…)

Llynn_and_Inner_Dowsing_large_image

Lynn and Inner Dowsing Wind Farms

June 2007 – June 2008

Lynn and Inner Dowsing are two adjacent wind farms which are situated 5km off the Lincolnshire coast, east of Skegness. They are each 90 MW wind farms which together are expected to provide power to 130,000 local homes. (more…)

Barrow_large_image

Barrow Offshore Wind Farm

July 2005 – May 2006

The Barrow Offshore Wind Farm (BOWF) comprises 30 wind turbines each capable of producing 3.0MW of electricity. The output for the whole site could be up to 90MW or enough electricity to power 87,000 average homes. (more…)

Horns Rev I – MPI Resolution

November 2004 – December 2004

During November 2004 and December 2004, MPI Resolution facilitated the transportation and installation of 11 Vestas V80 turbines on the Horns Rev 1 offshore wind farm.

Kentish_flats_large_image

Kentish Flats Offshore Wind Farm

August – October 2004

M.T. Hojgaard (MTH) awarded the subcontract to MPI Offshore in May 2004 for the load out, transport and installation of 30 WTG Monopiles and Transition Pieces. MTH crews, supported by MPI personnel, operated the foundation installation equipment. (more…)

North Hoyle – MPI Resolution

June 2003 – March 2004

Between June 2003 – March 2004, MPI was involved in the development of the North Hoyle offshore wind farm. (more…)