MPI Don Quixote currently working for EON on this project.

60 Vestas V90-3MW wind turbines are planned, with an offshore electrical substation and helicopter deck.
The 180 MW development will provide enough electricity for about 150,000 households.
The turbine foundations, each weighing 280 tonnes, consist of a steel monopile 50m long and 4.3 diameter. As well as the 60 turbine foundations there will be two substation foundations.
Click here for more information on the Robin Rigg Wind Farm
LATEST NEWS
MPI Celebrates Launching MPI Adventure Monday 6 September 2010
On 27 August 2010, MPI Offshore proudly held the launching ceremony of “MPI Adventure”, the first of two state-of-the art wind turbine installation vessels, currently under construction at the Cosco Nantong Shipyard in China.
READ MORE100 Turbines in less than 100 days Thursday 26 August 2010
More than a month ahead of schedule, Vestas completes the installation of the 100th turbine at the Thanet Offshore Wind Farm.
READ MOREMPI Workboats to exercise option for further workboat Wednesday 4 August 2010
MPI Workboats are happy to announce that it has exercised an option for the construction of a further state of the art, purpose built wind farm support aluminium catamaran for delivery in June 2011.